Customizing Items and Establishing Dependencies

Working With Items in Detail

After adding a task to your WBS, you can edit some task details on the WBS itself.

  • Click on the task’s Name to edit it.

  • Click on the task’s Planned Start, Duration and Planned End date to edit them.

  • To assign resources to a task, click on the task’s Assignments. For more information on assigning resources, see Assigning Resources to Tasks and Publishing Tasks.

  • Click on the task’s Labor Expense Type to edit it, and select an option from the drop-down list.

  • Click on the task’s % Complete to edit the number of hours a resource has spent on this task.

    • The Override Assignee Hours dialog will open. Click on the respective Planned Hours, Spent Hours and ETC to edit them, and click on Update.

      Note:  This option is available for customers who have elected to activate the Assignment Override feature. Contact support for more information.

  • Click on the task’s Predecessors to assign any task that must be completed before the selected one must be started.

    • The Edit Predecessors dialog will open. Locate the precursory task, click on the check box corresponding to this task, and click OK.

To edit a task’s aforementioned details and any other details as well:

  1. Click on corresponding to the task to open the Edit Task dialog.

  2. Edit any of the following details for this task as needed:

    Field Description

    Name

    Enter a name to identify the project.

    This field is mandatory.

    Ref#

    Enter any external Task ID.

    Description

    Enter a description of the purpose or nature of the task.

    Tracking Mode

    Select a tracking mode for this task:

    • Hours & ETC

    • EZ

    Duration Mode

    Select a duration mode for this task:

    • Fixed

    • Effort Driven

    Critical Path

    Click on the Critical Path check box, if you would like to manually place the task on the Critical Path. Note that the CP can also be calculated automatically.

    The following columns are available on the WBS:

    • CP

    • Planned CP

    • Projected CP

    Story Points Estimate effort and enter story points for this task.

    Planned Start

    Select the date the project is expected to start.

    Start Date Mode

    Select the start date’s mode:

    • System

    • Fixed

    • No earlier than

    • No later than

    Duration

    Enter the expected number of days to complete the task

    Planned End

    Select the date the project is expected to end.

    End Date Mode

    Select the end date’s mode:

    • System

    • Fixed

    • No earlier than

    • No later than

    Labor Expense Type

    Select the labor expense type for this task:

    • Inherit

    • OpEx

    • CapEx

    • DeferredEx

    Parent

    Select which phase or stage this task belongs to, from the drop down list.

    Assignments

    Locate the Resource you wish to add to this task and click on the Assign check box corresponding to the Resource. Enter the number of Planned Hours the Resource is expected to spend on this task.

    Checklist

    Click on the Add Checklist Item button, to add checklist items to this task.

    Fixed Costs

    Click on the Add New Fixed Cost button to add a new cost to the task. Click on the respective fields to edit details.

    Predecessor Dependencies

    Click on the check box corresponding to any tasks that must be completed before this task, i.e. other tasks that this task depends on.

    Successor Tasks Dependencies

    Click on the check box corresponding to any tasks that require this referenced task to be completed before they can begin, i.e. other tasks that depend on this task.

    Additional Parameters & Access

    Select any customers that this task is related to.

    If it is required to override access rights for this task, click on Inherit Access Rights from Project to deselect it, and select the relevant access rights for the task.

    Custom Attributes

    If existing attributes are listed, select the Attribute Value from the drop down.

    To add a new custom attribute, click on the Add New Attribute button.

  3. After all information has been verified, click on the Update button located at the bottom right of the page:

    • To clear all data that you have entered on the form, click on the Cancel button.

    • To clear any validation error messages, click on the Clear Validation button.

Establishing Dependencies

Dependencies define the relationships between tasks, indicating which tasks must be completed before others can begin. There are four types of dependencies:

  • Finish-to-finish: The previous task must be completed before the next task can be completed.

  • Finish-to-start: The previous task must be completed before the next task can start.

  • Start-to-finish: The previous task must start before the current task can be completed.

  • Start-to-start: The previous task must start before the current task can start.

"Loose" dependencies, which are not strictly enforced by the system, can also be established.